The Sunrise Release

Construction Commenced
September 2024
Estimated Title Registration
Late 2025

Civil Phase

  • EarthworksUnderway

    The first stage of construction involves the removal of topsoil, where it is then stored. The land is then shaped to the design levels in order to set the foundation for your new home.

  • SewerUnderway

    The construction of all trunk and reticulation sewers to provide sanitation services to each house lot.

  • Stormwater Drainage

    The construction of all stormwater pipes and pits which allow the safe draining of all stormwater away from the house lots.

  • Water & Gas

    The construction of water and gas pipes to each house lot, including all trunk and reticulation services.

  • Road Boxing & Base

    The base of the road is shaped and filled with engineered material to form a firm surface underneath the road pavement.

  • Power & Telecommunications

    The installation of power and telecommunications provide street lighting, power, internet and phone services to each house lot.

  • Road Kerb & Channel

    The concrete road kerbs are installed which form the edge of the new roads and help transfer stormwater into the drainage network.

  • Footpaths, Asphalt & Linemarking

    Concrete footpaths are constructed throughout the stage to provide safe pedestrian access to each house lot. The final step in building the new roads is the installation of the asphalt and linemarking, which provides the smooth driving surface for vehicles.

  • Practical Completion

    The completion of the construction works.

Registration Phase

  • Statement of Compliance

    The formal confirmation from Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

  • Lodge Plan of Subdivision

    The Plan of Subdivision has been lodged for registration at the Victorian land titles office, which creates the individual titles for all lots included on the Plan.

  • Titles

    The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor’s reports.

  • Settlement

    The legal transfer of the residential lot from the developer to the prospective homeowner.

01 /

Earthworks progress from above

Earthworks progress from above

Earthworks progress from above

Earthworks progress from above

Earthworks progress from above

Earthworks progress from above

01 /

The view from your backyard; sight lines to the iconic You Yangs mountain range.

Launch your boat close to home at the Clifton Springs pier.

The view from your front window; panoramic bay and city views to the West.

Treetop views from your front porch, across the beautiful Bellarine to the South.

Grab a coffee and start your morning at the Clifton Springs foreshore.

Some of the region’s best wineries are right on your doorstep.

Picturesque walking tracks, lakes and parklands are dotted throughout the community.

Download
Masterplan